Projects in Planning, in Progress, and Completed

Projects in Progress

Advanced Technology Laboratories Biomedical Engineering.Work started January 2004 with an estimated completion date of September 2006. Financing is from College of Engineering and Whitaker Foundation grant.

Ann Street Parking Structure. Work started March 2005 with an estimated completion date of September 2006. Financing is from parking resources.

Biomedical Science Research Building Animal Imaging Facility. Work started December 2005 with an estimated completion date of December 2006. Financing is from Medical School.

Bursley Residence Hall Infrastructure Updates and Dining Improvements. Work started December 2005 with an estimated completion date of March 2007. Financing is from University Housing and investment proceeds.

Cancer and Geriatrics Center and Medical Science Unit I Chiller Replacement. Work started February 2006 with an estimated completion date of September 2006. Financing is from central administration.

Central Power Plant Two Replacement Steam Turbines. Work started March 2005 with an estimated completion date of January 2007. Financing is from utilities reserves.

Dearborn-Engineering Laboratory Building Expansion and Renovation. Work started March 2005 with an estimated completion date of December 2006. Financing is from State Appropriation and UM-Dearborn.

Electrical Engineering and Computer Science Solid State Electronics Laboratory Addition. Work started April 2005 with an estimated completion date of December 2007. Financing is from College of Engineering, gifts and investment proceeds.

Engineering Research Buildings I & II Optics Group Laboratory Renovation. Work started February 2006 with an estimated completion date of December 2006. Financing is from College of Engineering.

Engineering Research Buildings I & II, Gerstacker Building, and School of Information North Building Boiler Replacement.Work started April 2005 with an estimated completion date of July 2006. Financing is from utilities reserves.

Fletcher Street Parking Structure Structural Repairs. Work started March 2006 with an estimated completion date of December 2007. Financing is from parking resources.

Ford Nuclear Reactor Decommissioning. Work started December 2005 with an estimated completion date of March 2008. Financing is from investment proceeds.

Harlan Hatcher Graduate Library—Emergency Power Upgrade. Work started October 2005 with an estimated completion date of September 2006. Financing is from utilities reserves.

Hoover Avenue Heating Plant Boiler Replacement. Work started January 2006 with an estimated completion date of September
2006. Financing is from utilities reserves.

Hutchins Hall Classroom and Administrative Office Space Renovation. Work started May 2006 with an estimated completion date of March 2007. Financing is from Law School.

Medical Sciences Research Building I Mass Spectrometer Laboratory. Work started March 2006 with an estimated completion date of October 2006. Financing is from Medical School.

Medical Science Unit I Anechoic Chamber Relocation Renovations. Work started December 2005 with an estimated completion date of September 2006. Financing is from Medical School.

Michigan Stadium 2006 Concrete Repairs. Work started November 2005 with an estimated completion date of August 2006. Financing is from Athletic Department.

Moore, Earl V. Building Corridor Ceiling and Lighting Upgrades. Work started May 2006 with an estimated completion date of December
2006. Financing is from central administration.

Oxford Housing Fire Alarm System Upgrade and Fire Suppression System Installation. Work started December 2005 with an estimated completion date of September 2006. Financing is from University Housing and investment proceeds.

College of Pharmacy Second and Fourth Floor Laboratory Renovations. Work started December 2004 with an estimated completion
date of October 2006. Financing is from NIH grant, College of Pharmacy, gifts and central administration.

College of Pharmacy Building Third Floor Laboratory Renovations. Work started March 2006 with an estimated completion date of
December 2006. Financing is from College of Pharmacy.

Stephen M. Ross School of Business Facilities Enhancement Project. Work started April 2006 with an estimated completion date of December
2008. Financing is from Ross School of Business and gifts.

School of Public Health Buildings Renovations.
Work started September 2003 with an estimated completion date of December 2007. Financing is from Investment proceeds, School of Public
Health and gifts.

South Quadrangle Elevator Controller Replacement. Work started April 2006 with an estimated completion date of December 2007. Financing is from University Housing.

South State Commons II, LLC Data Center Leasehold Improvements. Work started April 2006 with an estimated completion date of January
2007. Financing is from investment proceeds.

University of Michigan Hospitals and Health Centers Programs. Financing is from Hospitals and Health Centers.

Charles R.Walgreen, Jr.Drama Center. Work started May 2005 with an estimated completion date of September 2007. Financing is from gifts and investment proceeds.

Joan and Sanford Weill Hall. Work started October 2004 with an estimated completion date of October 2006. Financing is from investment proceeds, gifts and President’s discretionary resources.