202 South Thayer Building. Work started March 2005 with an estimated completion date of July 2006. Financing is from Central Administration; College of Literature, Science, and the Arts; and Investment Proceeds.
Ann Street Parking Structure. Work started March 2005 with an estimated completion date of September 2006. Financing is from Parking Resources.
Athletic Department Academic Center. Work started July 2004 with an estimated completion date of December 2005. Financing is from Athletic Department, Gifts, and Investment Proceeds.
Biomedical Science Research Building (BSRB). Work started February 2002 with an estimated completion date of December 2005. Financing is from Medical School and Gifts.
Central Campus and Medical Center Electrical Substation and Underground Distribution System. Work started November 2004 with an estimated completion date of December 2005. Financing is from Hospitals and Health Centers and Utilities Reserves.
Central Campus South Steam Line. Work started May 2005 with an estimated completion date of March 2006. Financing is from Utilities Reserves.
Central Power Plant Two Replacement Steam Turbines. Work started March 2005 with an estimated completion date of June 2006. Financing is from Utilities Reserves.
Chemistry Building Area Tunnel and Chamber Replacement. Work started May 2005 with an estimated completion date of March 2006. Financing is from Utilities Reserves.
Computer Science and Engineering Building. Work started November 2003 with an estimated completion date of November 2005. Financing is from College of Engineering and Gifts.
Couzens Hall Fire Alarm System Upgrade. Work started February 2005 with an estimated completion date of September 2005. Financing is from University Housing and Investment Proceeds.
Crisler Arena Replace Underground Steam and Condensate Piping. Work started December 2004 with an estimated completion date of September 2005. Financing is from Utilities Reserves.
Dearborn—Engineering Laboratory Building Expansion. Work started March 2005 with an estimated completion date of December 2006. Financing is from State Appropriation and U-M Dearborn.
Dearborn—Science Building Renovations. Work started October 2004 with an estimated completion date of February 2006. Financing is from State Appropriation and U-M Dearborn.
Dental Building and W. K. Kellogg Institute Elevator Replacement. Work started July 2004 with an estimated completion date of December 2005. Financing is from General Fund.
Dental Building and W. K. Kellogg Institute Third Floor Renovations. Work started February 2005 with an estimated completion date of August 2005. Financing is from Dental School and Central Administration.
Electrical Engineering and Computer Science/Solid State Electronics Laboratory Addition. Work started April 2005 with an estimated completion date of March 2007. Financing is from College of Engineering and Gifts.
Engineering Research Buildings I & II, Gerstacker Building, and School of Information North Building Boiler Replacement. Work started April 2005 with an estimated completion date of March 2006. Financing is from Utilities Reserves.
Junge Family Champions Center (Events Center). Work started January 2005 with an estimated completion date of November 2005. Financing is from Athletic Department and Gifts.
Edward Henry Kraus Building Renovate Rooms 1003, 1009, and 1012A. Work started February 2005 with an estimated completion date of December 2005. Financing is from College of Literature, Science, and the Arts.
Edward Henry Kraus Building Replace Elevators. Work started August 2004 with an estimated completion date of December 2005. Financing is from Central Administration.
LSA Building Renovations. Work started February 2004 with an estimated completion date of April 2006. Financing is from State Appropriation; College of Literature, Science, and the Arts; and Investment Proceeds.
Clarence Cook Little Building Renovate First Floor Teaching Laboratories. Work started March 2005 with an estimated completion date of September 2005. Financing is from Central Administration, College of Pharmacy, and Gifts.
Ann and Robert H. Lurie Biomedical Engineering Building. Work started January 2004 with an estimated completion date of September 2006. Financing is from College of Engineering and Whitaker Foundation Grant.
Medical School Magnetic Resonance Imaging Research Scanner. Work started February 2005 with an estimated completion date of October 2005. Financing is from Hospitals and Health Centers.
Michigan Stadium 2005 Concrete Repairs. Work started January 2005 with an estimated completion date of August 2005. Financing is from Athletic Department.
Perry Building Addition. Work started September 2004 with an estimated completion date of August 2006. Financing is from Institute for Social Research.
Pharmacy College Building Lab Remodel. Work started December 2004 with an estimated completion date of October 2006. Financing is from NIH grant, College of Pharmacy, Gifts, and Central Administration.
School of Nursing Building Renovations to First Floor of North Wing. Work started May 2005 with an estimated completion date of September 2005. Financing is from School of Nursing and Central Administration.
School of Public Health Buildings Renovations. Work started September 2003 with an estimated completion date of September 2006. Financing is from Investment Proceeds, School of Public Health, and Gifts.
Stockwell Residence Hall Elevator Replacement. Work started January 2005 with an estimated completion date of September 2005. Financing is from University Housing.
William Monroe Trotter House Infrastructure Upgrades. Work started April 2005 with an estimated completion date of September 2005. Financing is from Investment Proceeds.
Undergraduate Science Building. Work started August 2003 with an estimated completion date of December 2005. Financing is from Central Administration and Gifts.
University of Michigan Hospitals and Health Centers Infrastructure. Financing is from Hospitals and Health Centers.
University of Michigan Hospitals and Health Centers Programs. Financing is from Hospitals and Health Centers.
Charles R. Walgreen, Jr. Drama Center. Work started May 2005 with an estimated completion date of September 2007. Financing is from Gifts and Investment Proceeds.
Weill Hall, Joan and Sanford (formerly Gerald R. Ford School of Public Policy Building). Work started October 2004 with an estimated completion date of October 2006. Financing is from Investment Proceeds, Gifts, and President’s Discretionary Resources.
West Quadrangle Residence Hall 2005 Infrastructure Updates. Work started December 2004 with an estimated completion date of June 2006. Financing is from University Housing.
Wolverine Tower Electrical Substation Replacement. Work started October 2005 with an estimated completion date of July 2005. Financing is from Facilities and Operations and Central Administration.