PROJECTS IN PROGRESS


Vera Baits II Mechanical Infrastructure Renewal | Work started May 2008 with an estimated completion date of September 2009. Financing is from University Housing.

Camp Davis Rocky Mountain Field Station Cabin Replacement and Infrastructure Improvement | Work started December 2008 with an estimated completion date of September 2009. Financing is from College of LSA.

Central Campus Area Utility Tunnel and Piping Replacement 2009 | Work started April 2009 with an estimated completion date of December 2009. Financing is from utilities reserves.

Central Power Plant 2.4kV Switchgear Upgrade | Work started April 2008 with an estimated completion date of September 2009. Financing is from utilities reserves.

Central Power Plant Replacement Steam Turbine | Work started July 2008 with an estimated completion date of December 2009. Financing is from utilities reserves.

William W. Cook Legal Research Library Elevator Replacement | Work started February 2009 with an estimated completion date of June 2010. Financing is from investment proceeds.

East Quadrangle Residential College Auditorium Renewal | Work started April 2009 with an estimated completion date of December 2009. Financing is from College of LSA, gifts, and general fund.

East University Chiller Plant New Chiller | Work started August 2008 with an estimated completion date of September 2009. Financing is from investment proceeds.

Environmental and Water Resources Engineering Building Research Laboratories for Civil and Environmental Engineering | Work started May 2009 with an estimated completion date of December 2009. Financing is from College of Engineering.

Ford Nuclear Reactor Decommissioning | Work started December 2005 with an estimated completion date of July 2009. Financing is from investment proceeds.

Thomas Francis, Jr., Public Health Building Elevator Replacement | Work started September 2008 with an estimated completion date of March 2010. Financing is from general fund.

Thomas Francis, Jr., Public Health Building Infrastructure and Finishes Renewal | Work started April 2009 with an estimated completion date of December 2011. Financing is from School of Public Health and investment proceeds.

Indoor Practice Facility for Intercollegiate Football | Work started December 2007 with an estimated completion date of December 2009. Financing is from Athletic Department and gifts.

W. K. Kellogg Institute and Dental Building Exterior Repairs 2008 | Work started October 2008 with an estimated completion date of September 2009. Financing is from investment proceeds.

W.K. Kellogg Institute and Dental Building Information Technology Infrastructure Upgrade | Work started February 2009 with an estimated completion date of September 2010. Financing is from investment proceeds.

Michigan Stadium Renovation and Expansion Project | Work started July 2007 with an estimated completion date of December 2010. Financing is from Athletic Department and gifts.

Major ProjectsMichigan Wrestling Center | Work started October 2008 with an estimated completion date of December 2009. Financing is from Athletic Department and gifts.

Modern Languages Building Chilled Water Plant Expansion | Work started December 2008 with an estimated completion date of September 2009. Financing is from utilities reserves and general fund.

Earl V. Moore Building Infrastructure Improvements | Work started February 2009 with an estimated completion date of December 2009. Financing is from investment proceeds and utilities reserves.

North Quad Residential and Academic Complex | Work started December 2006 with an estimated completion date of September 2010. Financing is from University Housing, Office of the Provost, College of LSA, and investment proceeds.

Alexander G. Ruthven Museums Building Elevator Replacement | Work started February 2009 with an estimated completion date of March 2010. Financing is from general fund.

Madelon Louisa Stockwell Hall Renovation | Work started March 2008 with an estimated completion date of September 2009. Financing is from University Housing and investment proceeds.

Thompson Street Parking Structure Addition | Work started April 2009 with an estimated completion date of December 2010. Financing is from Parking and investment proceeds.

Towsley Center for Children Replacement Facility | Work started August 2008 with an estimated completion date of December 2009. Financing is from investment proceeds.

University of Michigan Hospitals and Health Centers Programs | Financing is from Hospitals and Health Centers.

  • Briarwood 2 and 4 Renovations | Work started September 2008 with an estimated completion date of September 2009.
  • Data Center Project | Work started October 2008 with an estimated completion date of June 2010.
  • Domino’s Farms Leasehold Improvements for the Division of Metabolism, Endocrinology, and Diabetes | Work started October 2008 with an estimated completion date of September 2009.
  • Eye Center Expansion | Work started January 2007 with an estimated completion date of March 2010. Financing is from Hospitals and Health Centers, Medical School, and gifts.
  • C.S. Mott Children’s Hospital and Women’s Hospital Replacement Project | Work started February 2007 with an estimated completion date of June 2012. Financing is from Hospitals and Health Centers and gifts.
  • A. Alfred Taubman Health Care Center Level B1 Medical Observation Unit | Work started December 2008 with an estimated completion date of September 2009.
  • A. Alfred Taubman Health Care Center Registration Area Renovations on Levels 1–3 | Work started January 2009 with an estimated completion date of December 2010.
  • A. Alfred Taubman Health Care Center Second Level Clinic Entry Renovations | Work started August 2008 with an estimated completion date of December 2009.
  • University Hospital Air Handling Upgrades | Work started February 2009 with an estimated completion date of March 2010.
  • University Hospital Computed Tomography and Interventional Radiology Expansion | Work started June 2008 with an estimated completion date of July 2009.
  • University Hospital Inpatient Bed Expansion – Unit 7A | Work started April 2009 with an estimated completion date of December 2009.
  • University Hospital Morgue Renovation | Work started February 2009 with an estimated completion date of December 2009.
  • University Hospital Positron Emission Tomography/ Computed Tomography Scanner Expansion | Work started May 2009 with an estimated completion date of December 2009.
  • University Hospital Process Chilled Water Expansion and New Cooling Tower | Work started May 2009 with an estimated completion date of June 2010.